Unauthorized use and/or duplication of text, photo and video material without express and written permission from IT Center Blog’s author and/or owner is strictly prohibited. Excerpts and links may be used, provided that full and clear credit is given to IT Center Blog with appropriate and specific direction to the original content.
Happy New Data Center!

The main event of 2016th year is here: we’ve change the data center. Our old one’s provider informed us about some troubles with uninterruptible power system. The data center is located in home zone which was built with tower blocks within last five years. The electricity limit is almost over so we decide not to wait for an end of this story.
So our hardware is located in AKADO Telecom data center Tier III certificated. It’s enough and to spare for IT Center Cloud services.
Based on the

Among them:
- Safely unmount and hardware encapsulation — 2 hours.
- Moving — 1 hour.
- Entering security procedures — 1.5 hour.
- Unpacking and hardware mounting – 2 hours.
- Hardware check and hierarchical load of IT Center Cloud services —1 hour.

Happy new home!